固结注浆法处理事故桩工程实录
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TU753.3

基金项目:


A Construction Example of Pile Amending by Consolidation Grouting
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    介绍了泉州刺桐大桥19号墩18号桩事故的处理,18号灌注桩由于灌注时导管断落使桩中出现一层约6.41米的事故层。采用固结注浆法进行处理,经检测效果良好,本文介绍了处理施工工艺与措施,可供类似工程 参考。

    Abstract:

    In this paper the amendment of No.18 pile in 19th pier of Citong Bridge in Quanzhou city is presented. There is a soft layer 6.41m thick in No.18 pile,a site cast concrete pile,due to breakdown of guide tube during casting. Amended by consolidation grouting, the pile stood up to tests. The construction technology, adopted steps and test method were introduced. It can serve as reference to similar engineering.

    参考文献
    相似文献
    引证文献
引用本文

许四发.固结注浆法处理事故桩工程实录[J].土木与环境工程学报(中英文),2001,23(5):81-84. XU Si fa The Second Bureau of Harbor, Channel Engineering, Wuhan, China). A Construction Example of Pile Amending by Consolidation Grouting[J]. JOURNAL OF CIVIL AND ENVIRONMENTAL ENGINEERING,2001,23(5):81-84.10.11835/j. issn.1674-4764.2001.05.017

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:2001-08-30
  • 录用日期:
  • 在线发布日期:
  • 出版日期:
文章二维码