Numerical simulation analysis on small clear spacing crossing viaduct pile foundation of shielded subway tunnels
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对南京地铁3号线部分路段小净距穿越高架桥桩基问题,适当简化后建立了隧道、管片及桩基的三维数值模型。模拟结果表明,地铁盾构小净距穿越高架桥对地表和桩基的受力和变形将会带来影响,地表最大变形量大于桩基顶部变形量,隧道右帮下侧管片出现应力集中。通过与现场监测结果对比,现场监测值与数值模拟结果吻合,建议今后施工时控制好施工参数,加强跟踪监测,必要时进行跟踪注浆加固。研究结果为本工程的顺利实施提供了参考。

    Abstract:

    Aimed at the problem of the in partial section of the Nanjing Metro Line 3, the three-dimensional pattern of tunnel, segment and pile foundation was established after appropriate simplification. The simulation results showed that, the Overpass pile foundation of Shield Tunneling to Adjacent Metro Shield Tunnel will have effect on the force and deformation of the earth's surface and pile foundation, the maximum deformation value of the earth's surface is larger than that of the pile foundation top, stress concentration appeared in right working slope lower side segment of tunnel. Through the comparison with field monitoring results, the field dates is consistent with the Numerical Simulation Results, the execution parameters are advised to be well controlled in the further construction, in the same time strengthing the track monitoring, tracking grouting reinforcement should be carried when necessary. The research results could provide reference for the smooth going of the project.

    参考文献
    相似文献
    引证文献
引用本文

吴晓腾,李海生,贾宝新.地铁盾构隧道小净距穿越高架桥桩基数值模拟分析[J].土木与环境工程学报(中英文),2012,34(Z2):61-64. Wu Xiao-teng, Li Hai-sheng, Jia Bao-xin. Numerical simulation analysis on small clear spacing crossing viaduct pile foundation of shielded subway tunnels[J]. JOURNAL OF CIVIL AND ENVIRONMENTAL ENGINEERING,2012,34(Z2):61-64.[doi]

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2013-03-07
  • 出版日期: