Abstract:On the base of the logic flow chart of the building construction's material request plan,the three prerequisites are given for MRP being introduced into building construction:the construction item's project schedule,the listing of the materials that will be used in the construction item and the information of the current stock in the construction unit must be gained. The prerequisites are also solved: the construction item's project schedule is made through network planning technology and database's programming; the listing of the materials is memorized according to the construction act; the up_to_date storage information can be gained by contacting to the storehouse's management department in time. Finally, the material request plan is drafted by the method of MRP.