Energy saving effect analysis of water system renovation in a coking plant
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    某焦化厂经过多次扩容后,冷却水系统容量没能跟上发展,冷却能力远低于运行需求,新水(自来水)消耗量远远高出国内外同行业水平。对其水系统进行改造,即新增两台容量为600 m3/h的冷却塔、修复当前冷却效果已经较差的2台的冷却塔,将循环冷却水温降下来,以减少循环冷却水系统的排水量和补充水量;增设废水回收利用管网,将原排放的废水用于熄焦补充水,以节省熄焦补充水对新水的消耗,多余的废水引入到集团公司炼铁厂使用。通过改造,焦化厂吨焦耗水从9.03 m3降至3.21 m3,每年节约用水量约为6×106 m

    Abstract:

    A coking plant extended many times, and its capacity of the cooling water system is not match with it, the consumption of new water is much more than that used by others in the same industry. The water system renovation is addressed for an extended coking plant. The installation of two 600 m3/h cooling towers and restoration the existing two cooling towers are to promote the cooling capacity so that the amount of discharge and feed could be reduced. At the same time, the pipe net for waste water reutilisation is installed, by which part of the waste water is reused as supplement water for quenching hot coke and the other was piped to ironworks for reuse. With the field test, the water consumption per ton of coke production is cut down from 9.03 m3 to 3.21 m3. And the annual water saving is more than 6×106 m3. Furthermore, the electric consumption is reduced by 2×106 kWh and about 3×106 yuan of annual running cost is saved.

    参考文献
    相似文献
    引证文献
引用本文

王德明,龙腾锐,宋长华,丁德渝.焦化厂节水改造及其节能效果分析[J].重庆大学学报,2010,33(1):104-108.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期:
  • 出版日期: